2016 | 10 | nr 1/2 | 31--43
Tytuł artykułu

Insertion Algorithms with Justification for Solving the Resource-Constrained Project Scheduling

Treść / Zawartość
Warianty tytułu
Języki publikacji
EN
Abstrakty
EN
The paper presents the resource-constrained project scheduling problem with the makespan minimization criterion. To solve the problem, the authors propose insertion algorithms that generate schedules with the use of forward serial and parallel decoding procedures. Schedules are improved with the use of the double justification by the extremes technique (first right and then left justification). The efficiency of the procedures proposed is tested on standard test problems from the PSPLIB library.(original abstract)
Rocznik
Tom
10
Numer
Strony
31--43
Opis fizyczny
Twórcy
  • State School of Higher Education of Biała Podlaska
  • AGH University of Science and Technology Kraków, Poland
Bibliografia
  • Błażewicz, J., Lenstra, J., Kan, A.R., 1983. Scheduling subject to resource constraints classification and complexity. Discrete Applied Mathematics, 5(1), pp. 11-24.
  • Brucker, P., Drexl, A., Mohring, R., Neumann, K., Pesch, E., 1999. Resource-constrained project scheduling: Notation, classification, models, and methods. European Journal of Operational Research, 112(1), pp. 3-41.
  • Demeulemeester, E., Herroelen, W., 1992. A branch-and-bound procedure for the multiple resource-constrained project scheduling problem. Management Science, 38(12), pp. 1803-1818.
  • Goncalves, J., Resende, M., Mendes, J., 2011. A biased random-key genetic algorithm with forward-backward improvement for the resource constrained project scheduling problem. Journal of Heuristics, 17(5), pp. 467-486.
  • Hartmann, S., Briskorn, D., 2012. A Survey of Variants and Extensions of the ResourceConstrained Project Scheduling Problem. European Journal of Operational Research, 207(1), pp. 1-14.
  • Hartmann, S., Kolisch, R., 2000. Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem. European Journal of Operational Research, 127(2), pp. 394-407.
  • Józefowska, J., Węglarz, J. (eds.), 2006. Perspectives in modern project scheduling, Springer, Berlin.
  • Klimek, M., Łebkowski, P., 2010. Algorytmy wstawień dla zagadnienia harmonogramowania projektu ze zdefiniowanymi kamieniami milowym. In: Knosala, R. (red.), Komputerowo zintegrowane zarządzanie, T. 1, Opole, Oficyna Wydawnicza PTZP, pp. 676-685.
  • Kolisch, R., 1996a. Serial and parallel resource-constrained project scheduling methods revisited: Theory and computation. European Journal of Operational Research, 90(2), pp. 320-333.
  • Kolisch, R., 1996b. Efficient priority rules for the resource-constrained project scheduling problem. Journal of Operations Management, 14(3), pp. 179-192.
  • Kolisch, R., Hartmann, S., 2006. Experimental Investigation of Heuristics for ResourceConstrained Project Scheduling: An Update. European Journal of Operational Research, 74(1), pp. 23-37.
  • Kolisch, R., Padman, R., 2001. An integrated survey of deterministic project scheduling. OMEGA, 29(3), pp. 249-272.
  • Kolisch, R., Sprecher, A., 1997. PSPLIB - a project scheduling library. European Journal of Operational Research, 96(1), pp. 205-216.
  • Nawaz, M., Enscore, E., Ham, I., 1983. A heuristic algorithm for the m machine, n-job flow-shop sequencing problem. OMEGA, 11(1), pp. 91-95
  • Tormos, P., Lova, A., 2001. A competitive heuristic solution technique for resource-constrained project scheduling. Annals of Operations Research, 102(1), pp. 65-81.
  • Tormos, P., Lova, A., 2003. An efficient multi-pass heuristic for project scheduling with constrained resources. International Journal Of Production Research, 41(5), pp. 1071-1086.
  • Valls, V., Ballestin, F., Quintanilla, S., 2005. Justification and RCPSP: a technique that pays. European Journal of Operational Research, 165(2), pp. 375-386.
  • Valls, V., Ballestin, F., Quintanilla, S., 2006. Justification technique generalisations. In: Józefowska, J., Węglarz, J. (eds.), Perspectives in Modern Project Scheduling, Springer, Berlin, pp. 205-223.
  • Valls, V., Ballestin, F., Quintanilla, S., 2008. A hybrid genetic algorithm for the resource-constrained project scheduling problem. European Journal of Operational Research, 185(2), pp. 495-508.
  • Woo, D.S., Yim, H.S., 1998. A heuristic algorithm for mean flowtime objective in flowshop scheduling. Computers and Operations Research, 25(3), pp. 175-182.
Typ dokumentu
Bibliografia
Identyfikatory
Identyfikator YADDA
bwmeta1.element.ekon-element-000171496470

Zgłoszenie zostało wysłane

Zgłoszenie zostało wysłane

Musisz być zalogowany aby pisać komentarze.
JavaScript jest wyłączony w Twojej przeglądarce internetowej. Włącz go, a następnie odśwież stronę, aby móc w pełni z niej korzystać.